Building a house on helical piles: when they beat footings, how caps and grade beams work, the ESR and permit path, per-pile costs and Canadian rules.

Yes, you can build a house on helical piles. The building codes treat them as an engineered deep foundation: steel piles are screwed down through weak or wet soil to a firm layer, and the house sits on a concrete grade beam or steel beams tied to new-construction caps on top of each pile. Installed prices for lightly loaded structures run about $400 to $2,000 per pile (US Helical Piers), and the engineer's pile layout, not the floor area alone, sets the total.
A spread footing works by pressing on the soil just below the frost line. Helical piles earn their cost when that near-surface soil cannot be trusted or cannot be reached easily. These are the common triggers:
The system has three parts: the piles, a cap on top of each pile, and a structural element that spans between caps and carries the walls.

Each pile is a steel lead section with one or more helix plates, plus plain extensions added until the pile meets its termination criteria. Under the CHANCE evaluation report (ICC-ES ESR-2794), the lead and extensions are installed until the torque and depth set in the foundation design documents are met, and the shaft can then be cut to the required elevation. For more on depth, read how deep helical piles go.
Foundation repair uses side-load brackets bolted to an existing footing, which carry compression only. New construction uses direct-load brackets instead. ESR-2794 describes these as Type B brackets embedded in concrete pile caps or grade beams, and says they support both tension and compression. Each one is a cap plate factory-welded to a steel sleeve that slides over the shaft. One listed model, for example, has a 1/2 in thick, 6 in square plate on a 6 in long, 2-1/2 in diameter sleeve.
The same report sets placement rules the builder must follow:
A reinforced concrete grade beam is the usual way to tie the caps together under a house: it spans from pile to pile and supports the walls. On expansive clay, the Colorado Geological Survey lists inadequate void space between soil and grade beam as a common construction error, because swelling soil that touches the beam can push it up. Steel beams bolted to the caps are another option, especially for raised homes, cabins and waterfront buildings. FEMA points out that a helical pile on its own gives little lateral resistance, so a strong moment-resisting connection to the foundation must provide it.
A helical foundation for a house is an engineered system, and the permit set reflects that. The usual sequence looks like this:
Hubbell's own summary of the IRC provisions in ESR-2794 notes that non-commercial new construction of light-frame homes can proceed without a geotechnical report or continuous special inspection. That is a code minimum, not a recommendation to skip soil data on a full house.
Every published number below is per pile installed or per foundation. None of them includes the concrete grade beam, the engineer's fees or the permit.
| Item | Published figure | Source |
|---|---|---|
| Per pile, lightly loaded structures | $400 to $2,000 installed | US Helical Piers |
| Per pile, new construction work | $350 to $900 installed | Helical Anchors, Inc. |
| Per pile, additions and light commercial | $500 to $1,200 | Helical Anchors, Inc. |
| Per pile, Canada (regional averages) | $300 to $500 (Ontario and Quebec), $400 to $600 (Alberta and B.C.) | Screw Piles Quotes |
| Custom home foundation, whole project | $16,000 to $25,000 (pile count not stated) | Screw Piles Quotes |
| Pile count, about 2,000 sq ft lightly loaded house on good soil | About 50 piers, plus or minus 10 | US Helical Piers |
The figures do not line up neatly, and that is the honest answer. The Canadian site's $16,000 to $25,000 home figure does not state a pile count or currency. Multiplying the US Helical Piers figures (40 to 60 piles at $400 to $2,000) gives a far wider spread of about $16,000 to $120,000 for the piles alone. That is our arithmetic, not a quote, and it shows why the pile count drives the budget.
Pile count comes from loads and spacing. US Helical Piers puts typical spacing for lightly loaded structures at 10 to 12 ft for slab-on-grade and 15 to 20 ft for suspended floors. Try your own numbers with the helical pier spacing calculator and the helical pile cost calculator, and see our full helical pier cost guide for depth extensions and mobilization fees.
Time is where helical piles often win back their price. A typical sequence is to install the piles, cut them to elevation, set the caps, then form and pour the grade beam.
For production rates per pile, see how long it takes to install a helical pile.
| Factor | Helical piles + grade beam | Conventional spread footing | Drilled concrete piers |
|---|---|---|---|
| Best soil | Weak, wet, expansive or variable soil over a firm layer | Good bearing soil near the surface | Firm soil or rock at depth, with dry, stable holes |
| Groundwater and sand | Installation not affected | Wet trenches may need dewatering | Groundwater and sand can complicate the pour |
| Load after install | Immediately, per pile | After concrete cures | At least 7 days to reach 75% strength |
| Capacity check | Torque recorded on every pile | Visual check of bearing soil | Visual check and inspection of the hole |
| Uplift resistance | Yes, with bolted new-construction caps | Weight of footing only | Set by pier depth and reinforcement |
| Cost | Higher than footings on good soil | Usually lowest on good soil | Somewhat less than helical piers, per US Helical Piers |
| Main drawback | Needs engineering, rated products and a specialty installer | Fails when shallow soil is poor | Spoil, concrete trucks and cure time |
Sources: US Helical Piers for cure time, groundwater and relative cost; ESR-2794 for tension caps. For a deeper comparison, read helical piles vs drilled piers and are helical piles better than concrete.
In Canada, helical piles are usually called screw piles, and for a house the approval route runs through the Canadian Construction Materials Centre (CCMC). The CCMC technical bulletin on auger-installed steel piles says a registered professional engineer must set the number and spacing of piles, a signed and sealed certificate of the installation and allowable loads is required for each project, installers must be certified by the manufacturer, and each pile carries a CCMC label.
Cities add their own rules. The City of Winnipeg's bulletin on helical, augured and screw piles in housing (2025-003-S R1, November 13, 2025) lists four requirements for constructing a new house on these piles:
Decks and one-storey additions at up to 5,000 lb per pile need fewer documents: the bulletin does not require a geotechnical report or an engineer's certification for them. Expect frost depth to set the minimum pile length in most provinces. Our screw piles guide covers the Canadian brands and terms.
We found no published insurer or lender rule that treats an engineered helical foundation differently from other permitted deep foundations, and we will not guess at underwriting. What we can say with sources:
Before you close on a lot or a finished home, ask your own insurance agent and lender how they handle pile foundations. Answers vary by company and region.
Bring these questions to your builder, engineer and pile contractor before you sign:
Our checklist on how to hire a helical pile contractor goes deeper. When you are ready for quotes, find a helical pile installer in your state or province, or browse our free helical pile tools.
Yes. Under the IRC, evaluated helical (screw) piles can serve as an alternate foundation system for light-frame construction when an engineer designs the system. In Canada, look for a CCMC evaluation and an engineer's sealed certificate.
The engineer's layout decides. US Helical Piers estimates about 50 piers, plus or minus 10, for a lightly loaded 2,000 sq ft structure on good soil, with spacing of 10 to 12 ft under slabs and 15 to 20 ft under suspended floors.
Published installed prices run about $350 to $2,000 per pile for new construction, plus the grade beam, engineering and permit. One Canadian guide lists $16,000 to $25,000 for a custom home foundation.
Not always under the IRC, if capacity is set from torque with a safety factor of 2.5 under the product's ESR. Many engineers and some cities, including Winnipeg for new houses, require one anyway.
On good, dry soil a spread footing is usually cheaper. On soft, wet, expansive or sloping ground, piles can cost less overall because they avoid deep excavation, dewatering and cure delays.
We found no published rule that says so. A permitted, engineered foundation with sealed drawings and installation records is the best protection. Ask your insurer and lender before you buy.
Last reviewed October 2026 by the Helical Pile USA editorial team. Found an error? Tell us.
Industry news, featured projects, new products, and installer spotlights from across the helical pile industry, delivered to your inbox.