How long does it take to install helical piles? Minutes per pile, piles per day for decks, new builds and repairs, and cure time vs concrete.

A single helical pile usually takes between a few minutes and about half an hour to screw into the ground, depending on depth and soil. A small deck is normally a one-day job, a crew on open new-construction ground can set dozens of piles a day, and foundation repair with excavation and a lift typically runs one to three days on site. Permits, engineering and inspections, not the screwing itself, set most of the calendar.
The turning itself is quick. The CHANCE helical pile installation instructions call for the pile to advance at roughly 3 inches per revolution and limit installation speed to less than 15 rpm. At those limits a shaft advances at most about 45 inches (under 4 feet) per minute, so pure turning time for a 20-foot pile is at least 5 to 6 minutes. A Pile Buck Magazine article gives a similar figure: at 6 to 10 rpm, about 30 seconds per foot and five minutes for 10 feet.
Real per-pile time is longer because the crew also has to locate and plumb the pile, bolt on extensions, record torque and depth, and cut and cap the shaft. Techno Metal Post puts a 6-foot residential pile at about 30 minutes. On the fast end, a CHANCE case history for a new single-family home reports 33 piers installed in 3 hours, or roughly 5 to 6 minutes each, against an estimate of 7 days for drilled, cased concrete piers.
For the order of the steps (layout, drive, torque monitoring, cutoff and capping), see our helical pile installation process guide. This page focuses on how long each part takes.
Daily production depends far more on the type of project than on the pile. Open ground with a machine that can drive straight to each location is fast. Work beside an existing house, where every pier needs a hand-dug pit and a bracket, is slow.
| Project type | Reported rate | Source |
|---|---|---|
| Deck or small residential structure | About 30 minutes per pile at 6 ft; most residential projects done in one day by a two-person crew | Techno Metal Post, Postech |
| New construction, open site | 33 piers in 3 hours (single-family home) | CHANCE case history |
| General production, operator plus laborer | Up to 30 to 40 piles a day, depending on the project | Pile Buck |
| Foundation repair with excavation and lift | 10 piers over two days, then a 30-minute lift | Dalinghaus project record |
| Deep piers in winter (existing home plus new work) | 37 piers to depths over 21 ft in less than five days | Supportworks case study |
Treat the top of each range as a best case. Manufacturer case studies are chosen because they went well, and a typical residential job includes setup, layout and cleanup time that a per-pile rate hides.
The install is the shortest phase on most jobs. The full schedule usually runs in this order:
| Project | Typical on-site time | What usually sets the calendar |
|---|---|---|
| Deck foundation | One day (Postech) | Permit review and the crew's schedule |
| Foundation repair with lift | One to three days (Ram Jack) | Engineering, permit, number of piers, excavation by hand |
| New home or larger building | Hours to a few days for the piles | Engineering, special inspection, pile count, depth |
To see how pile count and depth drive the price as well as the schedule, run your numbers through the helical pile cost calculator.
Concrete footings need time to gain strength before they carry load. Penn State's civil engineering course notes, which draw on the Portland Cement Association's Design and Control of Concrete Mixtures, state that for most structures the curing period above 40°F should be a minimum of 7 days or until 70% of specified strength is reached. With high-early-strength concrete above 50°F, that can drop to 3 days. In practice, even if footing holes are dug, inspected and poured on day 1, a 7-day cure puts framing on day 9 at the earliest (day 5 with a 3-day cure), while a helical pile deck can be framed on day 1. Concrete left to dry in air gains only about 50% of the strength of continuously moist-cured concrete, so skipping the cure is not a safe shortcut.

| Step | Helical pile deck foundation | Poured concrete footing |
|---|---|---|
| Holes | None; pile is screwed in | Dig each hole to frost depth |
| Inspection | Torque and depth recorded per pile | Holes are commonly inspected before the pour |
| Install or pour | About 30 minutes per 6 ft pile | Form and pour |
| Wait before loading | None once torque and depth are met | 7 days minimum curing (3 days with high-early-strength mix above 50°F) |
| Framing starts | Same day (Postech, Techno Metal Post) | After the curing period set by the spec |
Your project's engineer or specification sets the exact cure requirement, and some contractors frame earlier on footings than others. The point is that a helical pile carries its load as soon as it reaches the required torque and depth. For a wider comparison, read are helical piles better than concrete.
For a deck or new structure, expect a compact machine or mini excavator with a hydraulic drive head, a trailer of steel shafts, and a small crew. Piles are set one by one at marked locations. Each pile is turned in, extensions are bolted on as needed, and the installer reads torque at the end of each pile. There is no stack of dirt from digging holes and no concrete truck. When the last pile is cut and capped, framing can begin.
For foundation repair, the day is busier. Pits are dug along the wall at each pier location, brackets are attached to the footing, and piers are driven next to the house. If a lift is planned, the crew ties the piers into a hydraulic system and raises the structure while someone tracks elevations, then backfills the pits. You can usually stay in the home, but expect noise, a trench line along the foundation and some landscaping to replace. Our guide to helical piers for foundation repair covers the repair side in more detail, and helical piles for decks covers decks.
Only a local crew that has looked at your soil, access and pile count can give you a firm date. Ask each bidder for a written schedule that separates engineering and permit time from field days, and states how many piles they expect to set per day. You can find a helical pile installer in your state or province in our directory, and use our checklist on how to hire a helical pile contractor.
Most residential deck foundations are installed in one day. Techno Metal Post puts a 6-foot pile at about 30 minutes, and framing can start the same day because there is no cure time.
Anywhere from about 5 on a foundation repair with excavation to 30 or more on an open new-construction site. One CHANCE case history reports 33 piers on a new home in 3 hours.
Ram Jack says most repairs take one to three days on site. Engineering and permits before the work can take longer than the repair itself.
Yes. Once a pile reaches its required torque and depth it can take load, so there is no equivalent of the 7-day minimum concrete curing period.
Deep soft soil that needs extra extensions, buried obstructions, rock, tight access, frozen ground and any load testing the engineer orders when torque readings are in doubt.
Usually not by much. Piles can be installed year round, though frozen ground may need pre-drilling or thawing first.
Last reviewed October 2026 by the Helical Pile USA editorial team. Found an error? Tell us.
Industry news, featured projects, new products, and installer spotlights from across the helical pile industry, delivered to your inbox.